Will the Green Line Extend to Harohalli?

Yes, BMRCL has proposed a 24 km Green Line extension from Silk Institute to Harohalli along Kanakapura Road, but the corridor is not yet approved for construction. Aarvee Associates received the ₹1.59 crore consultancy contract in July 2024 to study this route along with the Challaghatta–Bidadi and Bommasandra–Attibele extensions. The Harohalli feasibility study was completed by late 2026, but the project still requires government selection, a Detailed Project Report, funding approval and construction tenders.
The operational Namma Metro Green Line currently runs 33.46 km through 32 stations from Madavara to Silk Institute. No final alignment, intermediate station list, project cost or opening date has been announced for Harohalli. For residents of Prestige Falcon City Reserve, the extension would be an additional southbound benefit; the project already has Metro access through the working Konanakunte Cross station, about 400 metres from the township entrance.